July 2, 2015
Build Time Today: 4 hours
Total Build Time: 67 hours
Got back to the build today after 2 days off. I was able to get the
brake and clutch lines riveted to the chassis along the sides, and also
finally riveted the final panel - the engine bulkhead panel. I have left
some off the rivets off the bottom (clecoed in place) so that the future
fuel lines that will need to share the rivets can all be put in
together. Similarly, I also did not rivet the entire top of the engine
bulkhead but just clamped it in place, so that the bodywork can
eventually fit on top and then all be riveted together.
Once all that was done, I finalized the fitment of the pedals, and also
attached the LS throttle sender - this little piece of equipment took an
entire TWO hours!! 3 rivnuts that need to be installed in the top
chassis bar - the location made it difficult to drill, and the rivnuts
once installed were out by 1mm (height wise) and it took a while to get
the bracket installed with a lot of filing and refitting required.
However, the bracket and throttle sender were eventually installed, and
now I can move forward...
July 3, 2015
Build Time Today: 3 hours
Total Build Time: 70 hours
Today saw the final panel being fitted! The custom radiator back
bulkhead panel was fitted in preparation for the radiator install. Once
installed, I finished up installation of the battery and battery clamp.
Then I started preparing the radiator - it was first placed in the
chassis and the holes were drilled for the bobbins to fit. The hole were
drilled into longer slots to allow the radiator to move a little during
final fitment. I then proceeded to install the fans (new EVO push type)
underneath the radiator using the nylon ties provided. Finally, I
finished up the day by checking the fitment of the radiator installs and
riveting them into the chassis. Tomorrow will see the radiator being
installed!
July 4, 2015
Build Time Today: 2.5 hours
Total Build Time: 72.5 hours
I started the day today with installing the radiator. It was placed in
the chassis and foam tape was cut for the entire bottom and the sides
(near the ears). The radiator was removed, foam tape placed, and
radiator re-installed. I had to be careful to get the wires to the
'front' side as I have the old CanAm loom, which has the radiator
connectors on the front side. I made sure to keep place for this in the
foam tape, and when the radiator was bolted down, the wires were
perfectly placed for the connections. I placed a corrugated cardboard
on the radiator for safety and started work on the cooling system.
The long aluminum pipes were threaded in the chassis, and the ally
P-clips were drilled on the table and then placed around the ally pipes.
The chassis was drilled, and then the rubber inserts were installed as
well. The P-clips were not riveted as the pipes need to be removed for
insulation before final install.
July 5, 2015
No work today as there was live relay...
July 6, 2015
Build Time Today: 4.5 hours
Total Build Time: 77 hours
Spent quite a bit of time in the workshop today. First order of business
was finishing the install of the cooling pipes. I removed the ally
pipes, and wrapped them in titanium exhaust wrap - to prevent heat from
entering the passenger cabin. My wife gave me a hand with this as it is
really a two person job to get a good tight wrap. Once the wrap was on,
the pipes were offered back to the chassis. I then installed the two
silicon connectors to the radiator, and then finally riveted the pipes
onto the chassis.
After the cooling system, I decided to work a little on
the interior. So I setup the gear change mechanism and the handbrake.
For the Porsche gear change, all the bits and bobs were retrieved from
the boxes, and installed as per the manual. It took quite a bit of
fiddling to get the mechanism to install on the base plate due to
incorrect alignment of holes. However, at the end it was ok. I then
threaded the cables from the engine side to the interior and installed
them onto the supports. Final fitment of cables will be done when the
gearbox is installed.
After the gear change, I installed the handbrake -
fairly simple: Setup the handbrake with all the small pieces, and then
bolt it to the chassis. Again pass the cables from the engine side, and
install onto the supports. The ends were then connected to the handbrake
lever. I also took a moment to check clearance for the central GRP cover
(over handbrake and gear change) - it needs to be filed and holes cut
out, which I will leave for tomorrow.
Final job for the day was installing the driver dead
pedal - can be seen in the last picture to the left of the clutch. It
has also been powder coated black.
July 7-9, 2015
Build Time Today: 5 hours
Total Build Time: 82 hours
I was not able to edit the website so this will cover
work for the past 3 days - which admittedly has been very slow.
First I installed the small rubber vent pipe for the
radiator, the radiator water temperature sensor and the horn.
Then I decided to work on the steering system - I
extracted the rack from the box, placed the clamps on it, and slowly put
the entire thing in the chassis and somehow got the bolts on - all with
just a pair of hands (this is one step where HELP is beneficial). It
took a while to get the rack on as I was working alone, but its finally
on there. I left the bolts a little loose to allow fitting of the
steering column - which will have to wait because I have not yet
received the column from the factory. There is a delay on my order, and
I am hoping to receive it soon. I also installed the two rubber bearings
for the upper steering column.
I then started work on the loom - the spaghetti roll was
laid out of the ground, and all the wires were pain-stakingly marked for
future reference. The loom was then put on the chassis in a rough
position.
The engine bay now needs to be cleaned up a bit before I
get back to adding additional parts. The handbrake cables, gear change
cables, battery cables, wiring loom, brake and clutch lines all need to
be drilled and clecoed into place. I will do this tomorrow, and then get
back to the build next week.
July 10, 2015
No work today
July 11, 2015
Build Time Today: 3 hours
Total Build Time: 85 hours
I spent most the afternoon today cleaning up the engine bay - all
cables, lines and wires were drilled and either riveted or clecoed to
the chassis. I took a while and a toll on my back, having to bend over
the chassis to drill and rivet the lines in...
July 12, 2015
Build Time Today: 6 hours
Total Build Time: 91 hours
Today was a long day in the garage.
First, I spent about 3 hours getting all the bushes and sleeves into the
front and rear wishbones. This took a long time as the bushes did NOT
want to go in, even with a generous helping of grease and a vice. Slowly
but eventually, I was able to get all the bushes and sleeves in.
I then got to work with the front wishbones. The chassis support were
separated with a rubber mallet, and wishbones installed with more grease
on the sides, and copper ease on the bolt. It again took a while to get
the supports opened sufficient for the wishbones. A general tap with a
drift was required on the lower ones to get them to open up completely.
Once installed, the bolts were torqued up to 35 ft/lbs.
July 13, 2015
Build Time Today: 4 hours
Total Build Time: 95 hours
I started off today with completing the rear wishbones. I had to post a
question last night on the Ultima forum because the lower rear wishbones
would not fit - apparently, the new chassis design has a steel support
on the lower wishbone mounting lugs, and this support makes separating
the lugs difficult. The support is also welded in and there was quite a
bit of weld splatter that would not let the wishbone in. A lot of filing
later, I was finally able to get both rear wishbones in.
Once done with the wishbones, I worked on the front and rear uprights -
simple as bolting them in. For the time being I have not torqued them
until I am done with the initial suspension alignment.
July 14, 2015
Build Time Today: 6 hours
Total Build Time: 101 hours
A month today in the workshop! And I hit 100 hours!
Spent a long time in the garage today trying to get the rear rotor on -
took me 6 hours to do one side!! I was having problems all day - the
holes on the rotors were too small for the lugs, the center hat would
not go all the way back and sit flush with the upright, and then I could
not get either the brake or handbrake calipers to sit straight...
A lot of hammering, cussing, (some bleeding) and a day later, I have
finally got the rear left rotor on... now I also know how better to
approach the other three...
July 15, 2015
Build Time Today: 5 hours
Total Build Time: 106 hours
Well I definitely must have learnt something yesterday - because I was
able to get the other 3 rotors on within 3 hours today. Still longer
than it should take, but that was because I had to drill out the holes
and file the center part to get the rotors to sit properly on the hubs.
I also dry fitted all four brake calipers and both handbrake calipers.
Those were immediately removed, and will be installed after the initial
alignment (forgot to take pic with the brakes on)...
The next thing I tackled today was the fitment of the center console.
This again needed alot of filing of the ally gear change base plate, and
of the GRP center console itself. A lot of filing, sawing, sanding, and
trial fitting later, I had the center console fitting correctly. Only
the seat belt bolt holes need to be drilled, but those will be done
later when I fit the seats...
July 16, 2015
Build Time Today: 3.5 hours
Total Build Time: 109.5 hours
First job for today was the fitment of the dampers. It took over an hour
to fit all four, but that was primarily because I was working alone and
had to juggle holding the damper in place with one hand, holding the
wishbone in place with the other, and then inserting the bolt with a
washer, thought he chassis hole, into a spacer, into the damper, through
another spacer, pass the second chassis hole and then tighten with a
washer and bolt - it would probably be a lot easier with help!
Once the dampers were in, I decided to open another box - the AC!!
Fitting of the AC base plate was done with the usual mark chassis
members, drill, drill chassis, debur everything, waxoyl, sikaflex and
then rivet. The location of the base plate took a little while as I had
to refer to the build CD and various other build sites to make sure I
was putting it in the right place.
Once the base plate was in, I added a bit of the foam tape inside to
prevent the blower unit for rattling, and installed the blower unit with
a pair of floating bolts. The hoses for the AC and the heater were then
passed through the chassis members and left for installation tomorrow.
July 17, 2015
EID Mubarak! Spent the day visiting family and friends to celebrate Eid...
work will continue tomorrow...
July 18, 2015
Build Time Today: 5.5 hours
Total Build Time: 115 hours
Spent the morning finishing up the AC and heater connections - the
heater hoses were dipped in boiling water and then threaded on to their
ports on the blower, and tied down with clips. The AC hoses were fitted
with the green O-rings, the thermostat installed on the lower AC pipe
with the sensor and sticky tape put back into the blower housing unit,
and then both AC hoses were tightened down with the large screws. The AC
and heater hoses were then zip tied along the chassis all the way to the
engine bay alone the sides in preparation for the luggage container.
I then spent a few hours pre-fitting the luggage containers. The factory
does a good job in getting the basic notches taken care off, but there
was still quite a bit to remove from the corners, for the AC/heater
pipes, and along the bottom outer side where the radiator pipes go back
to the engine. The passenger side fitted on quite well, but the driver
side would not fit - it became apparent that my radiator pipe was
sitting too high and the luggage pod would not be able to fit over it...
which means I will need to remove the radiator pipe rivets, lower the
whole thing, and retry everything - which I am leaving till tomorrow as
I am tired on the luggage pods now...
Instead I decided to work on the Cill Covers - now these are the MOST
IMPORTANT panel on the car... they are the first thing you see when you
open the door, so they have to be perfect. I decided to make a template
from the factory cill cover, and then trim and fit that until I got a
perfect fit. The template was then transferred to the cill, and the cill
will be cut into shape tomorrow.
Final job for today was going over all the interior electric connections
on the loom and making a note for all the interior holes that will need
to be cut into the centre section of the GRP. I studied the paperwork of
the loom, went through the switches, and edited my notes to account for
the stack display and the stalks that I will be using - my list now
stands at about 25 holes - 5 for stack (stack + 4 buttons), stalks, AC
controls, AC vents, ignition/push button, radio, some extra switches for
mods, and 5 light bulbs - the light bulbs might eventually also be
replaced with a light 'stick'...
A long day in the garage today - tired, so will be back tomorrow...
July 19-21, 2015
Build Time Today: 7 hours
Total Build Time: 122 hours
This is an update for the last 3 days: Didn't get much work in as real
work has kept me busy. However, I spent a little bit of time in the
garage the last few days and was able to do the following:
The luggage pods were drilled for holes for a pvc pipe (back to front)
for future wiring - on both sides. The driver pod was also drilled for
four latch cables. Finally, both pods were drilled for the cable tie
holders. The pods were then placed on the chassis, and chassis drilled,
deburred and waxoyled. The radiator pipe was also lowered a bit to allow
the drivers side pod to fit. The pods were then covered with insulation
on the outside, and black carpet on the inside - the first bits of
interior trim are now on!! The pods are now ready for final fixing -
which will hopefully be done tomorrow.
Also, time was spent on leveling the chassis on the dolly - it took a
while, as the rear passenger side was lower by almost 5mm that the rest
of the chassis - I guess either my floor isn't level, or the dolly
isn't... anyway, the chassis was finally leveled, and the preliminary
alignment can now be carried out - again a job for later this week.
Finally, I spent a little time trimming the cill cover in place. They
are still not 100% done, but the time spent on this will pay off as they
need to be perfect!
Also, sharp eyes will notice that I have three hoses/cables running on
the passenger side - 2 AC hoses, and the LS engine loom. I layed the
loom out from now along with the AC hoses, so that the luggage container
can be trimmed for all 3 together, rather than have to cut a separate
hole in the future. This will also save me from having to work inside
the pod...
July 22, 2015
Build Time Today: 4 hours
Total Build Time: 126 hours
Another long day in the workshop. I was able to get quite a bit done...
First, the luggage containers were riveted to the chassis. The usual
combination of sikaflex and riveting most of the time today - I was not
able to get a drill or rivet gun into the engine facing side, so ended
up drilling a larger hole from the outside and securing that end with a
bolt/nut. Both luggage containers were finally in! I also installed the
4 canopy latch release cables, and ran some extra wires and rope inside
the pvc pipe for future wiring.
I then got both cill covers trimmed and fitting perfectly. The cill
covers were then marked for matching rivet holes from the side ally
panels. That done, I decided to call it a day.
July 23, 2015
Build Time Today: 6 hours
Total Build Time: 132 hours
A long day in the workshop again!
Started the morning with getting the preliminary alignment done... First
I created a box using 2 straight steel box bars and some rope. The box
was then used to align each individual wheel - first toe (set to zero),
then camber (also set to zero), re-adjust toe and camber until both were
exactly straight ahead and vertical. All four wheel were done, and then
all the bolts were tightened down as per specifications - bolts for
wishbones, dampers, uprights, and steering rack.
Once the alignment was done, I then proceeded to install the AP brakes
and handbrakes. The calipers were mounted onto the brackets with loctite,
and the pads and anti-rattle clips were then installed. The brake lines
were installed into the calipers. Handbrakes were similarly installed,
with the handbrake cables also being connected to their clips. All done,
and I almost have a rolling chassis (save the steering column which is
still pending to receive from Ultima)
July 24, 2015
Build Time Today: 5 hours
Total Build Time: 137 hours
Today I finally started to work on the body!
The driver side pod was the goal of the day... First, I placed it on the
chassis using the factory pre-fit marks, and marked for the front
radiator pipe area which needed to be cut away. The area was slowly
nibbled, and the side pod trial fitted on the chassis again and again
until a very close fit was found. I would say it took about 6-7
iterations before the cutout was perfect. Once the side pod was sitting
properly, I marked the bottom edges for the chassis rails using some
basic match. The side pod was then drilled for rivet holes, and the side
pod then placed on the chassis, and the chassis drilled and waxoyled. My
math paid off because the chassis holes are placed perfectly on the
lower rails!
I then started work on the passenger side pod. It was similarly placed
on the chassis and the area for the return radiator pipe was cut out.
Once perfect, I marked the bottom edges for the rivet holes. Drilling
the holes in the pod and the chassis will be done tomorrow.
July 25, 2015
Build Time Today: 5 hours
Total Build Time: 142 hours
The passenger side pod was drilled, and then placed on the chassis and
the chassis drilled as well. The chassis waxoyled, and both side pods
were put on the side while I prepare the fuel tanks - the tanks need to
be installed before the side pods are final riveted onto the chassis.
The fuel tanks were prefit to check for clearance of the radiator pipe,
and then covered with paper and tape so that the non-visible parts can
be painted with tough black. Once the tanks were dry to touch, I took
them back into the workshop and started covering them in DEI Gold - an
extreme heat insulation to help keep the fuel cold during use. Then the
VDO fuel level sensors were installed, taking care to remove the pin
from each sender before inserting it into the tank.
After the tanks, I decided to work a little more on the cill covers. The
ally spacers that sit between the cill and chassis were glued to the
cill cover using the sikaflex. A little extra is on there, but that will
be removed when I CF the cill cover tomorrow.
July 26, 2015
Build Time Today: 2 hours
Total Build Time: 144 hours
A real short day in the workshop. I basically only had time to do a few
small things:
I installed the electronic heater valve. I am not using the Ultima pull
cable valve, instead I have sourced a 4-port electric valve that
opens/closes with a turning knob. The valve itself was installed the
driver luggage container where the heater hoses run through.
After that, I taped up the side pods, and painted them with the tough
black on the inside. Once painted, I left them to dry for the day
July 27, 2015
Build Time Today: 3 hours
Total Build Time: 147 hours
The fuel tank and side pods were fitted to the chassis (temporarily) so
that I could start work on the engine bulkhead panel. I am still waiting
for the final parts from Ultima (including the grill mesh) so I cannot
rivet the sidepods yet.
The center rear section was then temporarily put on the chassis, so that
I could mark the rivet lines in the middle. Then I removed the center
section and laid it on the floor to mark all the holes required for the
swirl pot, expansion tank, AC drier, regulator, and cable ties. After
marking the section, I called it a day and left the drilling for
tomorrow.
I am doing the center section holes together because I will having the
car interior installed soon, and I don't want to have to drill through
the leather later on. Thus by making all the holes now, I can safely
trim the interior without worrying about having to drill more holes.
July 28, 2015
Build Time Today: 6 hours
Total Build Time: 153 hours
Despite spending almost all day in the garage, at the end of the day
there seemed to be NO visible progress! It was just one of those days:
All rear center section holes were all drilled, including the lower line
rivet holes which will overlap the ally engine bulkhead. I had ended up
double checking a lot of holes to make sure they were in the right
place, because space in the engine bay is at a premium and I had to make
sure the positioning was correct so that the engine could fit later on.
After the rear center section holes, I decided to continue with the same
strategy and ended up marking and drilling all the holes on the engine
bulkhead - holes for the radiator, cooling, heating hoses, electrical
wires, cables, fuel pump and filters. The only holes not yet marked or
drilled are for the Pollack valve, which I will try and get to tomorrow
when I start installing the items on the bulkhead.
So despite a lot of marking and drilling, there seems to be no visible
progress today (except a bunch of holes)!!
July 29, 2015
Build Time Today: 1 hours
Total Build Time: 154 hours
Just a short stop in the garage today to finish up the engine bulkhead
drilling - I drilled the holes for the Pollack 2-tank change over valve,
and also fitted the rivnuts for the valve and HP pump. Thats it for
today!
July 30, 2015
Build Time Today: 3 hours
Total Build Time: 157 hours
Today I started work on the electrical system!!
First thing was to start connecting the stalk kit - AutoBionics has
supplied a very nice stalk kit made up of a Ford stalk unit and a custom
wiring harness that connects to the Ultima wiring harness. It took a
while to get the harnesses laid correctly on the chassis, and then it
was a matter of checking both the AB and the Ultima harness drawings to
figure out which wires to cut, solder, tape over, etc... Now the stalk
kit is connected and ready to test in a couple of weeks once I have most
of the wiring connected
Next I started to work on the seats - I have only ordered the seat
shells, and will get them trimmed locally. First thing was to install
the runners - which was done and the seats were then sent to the
trimmer, so that they can be installed later
While at the trimmer, I also picked up the first piece of my leather
interior - it will be glued and installed tomorrow.
July 31, 2015
Build Time Today: 7 hours
Total Build Time: 164 hours
First thing for today was installing the leather on the rear bulkhead -
it looks amazing!
Next thing on the agenda was the side pod trim sections: both the
passenger and driver side pods have small GRP sections that are moulded
to sit in front of the side pod, behind the wishbones. They provide
protection against the elements, and also complete the wheel well.
These small trim parts take A LONG time to fit - they must be trimmed in
3-dimensions, with cutouts made for the chassis, radiator pipes, battery
cables, clutch/brake pipes, etc... Almost 6 hours was spent getting the
two trim sections to sit correctly, and then the trim sections were
drilled as required and attached to the chassis with clecoes. They will
riveted on after the side pod is finally installed.
|